1. Resources for the Madison Community

    Madison stands with the families of Abundant Life community. This page is dedicated to connecting victims and the broader community to resources and accurate information about the tragic events that happened on December 16.

Warner Park Community Recreation Center Expansion

December 17, 2024 Update

Watch the construction progress of the Warner Park Community Recreation Center's Expansion available on the live construction site camera.  

View past project updates »

Project Details

  • Location

    • 1625 Northport Dr
      Madison, WI 53704
  • Project Type

  • Status

    Bidding
  • Estimated Schedule

  • Alder District

    District 12
  • Contract Number

Project Information

Project Overview

This project consists of public engagement and the design and construction of an expansion to the existing Warner Park Community Recreation Center building located at 1625 Northport Drive, Madison, Wisconsin 53704. The building is located in Warner Park near Northport Drive and the Mallards Ballpark. Since the original construction, the need for community recreation and program areas have increased and the building requires an expansion of space. A Programming and Facility Study was completed in 2017 to develop programming needs and options for expansion. The study also documented the need for system upgrades, general performance improvements, accessibility and other health and safety compliance modifications, workspace updates, architectural upgrades, leased space improvements, and site improvements. Please visit the City of Madison Parks project page here for more information about this project's history.  The current project will determine the expansion needs through a robust public engagement process. The public outreach will guide the design of the facility addition.

November 16, 2022 Update: Parks held a virtual public meeting to present the pre-design community input gathered over the last several months.  Public outreach consisted of an online survey (in English, Spanish and Hmong) open through October 31, 2022, and a series of virtual stakeholder meetings. The findings from the survey and the stakeholder discussions were presented at a public meeting on November 14, 2022.  The presentation slides are available here: Warner Park Community Recreation Center Expansion Project Virtual PIM #1 Meeting Presentation Slides.  The next community meeting is anticipated during the project's schematic design phase.

February 01, 2023 Update: Engberg Anderson Architects is working with city staff to develop an expansion project that addresses the Center’s multiple needs identified during the public engagement process. The team has worked through the Pre Design phase and completed the Pre Design Report which documents the public engagement feedback, the values and goals statements, the analysis of data and needs, the design direction, and the anticipated project schedule.  The Pre Design Report can be found here: WPCRC Expansion Pre-Design FINAL Report and Appendix. The team is starting on the Schematic Design phase which will develop the building massing, floor plan, and scope of interior changes.

May 01, 2023 Update: Engberg Anderson Architects and city staff have completed the Schematic Design phase and are moving into the Design Development phase. The team has completed the Schematic Design report which documents the data analysis and feedback used to develop various design options and the ultimate design direction for the expansion project. The Schematic Design Report can be found here: WPCRC Expansion Schematic Design Report and Appendix.

July 05, 2023 Update: The project is being reviewed by Focus on Energy and the City’s Commissioning Consultant to ensure that sustainable energy efficient systems are being planned for the expansion project. Engberg Anderson Architects and city staff will complete the Design Development phase in September and then move to the Construction Documents phase. Bidding will likely occur in January.

October 02, 2023 Update: The project progress slowed, but is now moving forward again. The design development phase will be complete at the end of October. The Parks Division would like to redesign the mechanical system to utilize a geothermal system. The project will likely bid in the first quarter of 2024.

Project Schedule

City User Agency: City of Madison Parks

A/E Consultant RFP Advertisement: May 05, 2022
A/E Consultant RFP Due Date: June 02, 2022
RFP documents can be found on VendorNet and DemandStar
"All information regarding dates/times/locations are informational and should be verified with the RFP documents"

Planning and Design: September 2022 - April 2023

Construction and Bid Doc Preparation: April 2023 - August 2023

1st Advertisement of Bid: May 17, 2024 available only on Bid Express

Contractor's Bid Talk (Virtual): Friday, May 31, 2024 @ 11:00 a.m.
May 31, 2024 Bid Talk Recording
Bid Talk WPCRC Presentation

Pre-Bid Project Tour #1: Wednesday, May 29, 2024 @ 2:00 p.m. at the project site (1625 Northport Drive, Madison, WI)

Pre-Bid Project Tour #2: Thursday, June 06, 2024 @ 2:00 p.m. at the project site (1625 Northport Drive, Madison, WI)

SBE Pre-Bid Meeting (Virtual): Thursday, June 20, 2024
Preregistration is required at SBE Pre-Bid Meetings

Bid Due Date: Thursday, June 27, 2024
Construction Start Date: August 12, 2024
Expected Completion Date: December 31, 2025

"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations will be indicated below as this project progresses.

Public Information Meetings

March 27, 2023 Public Information Meeting #2 Presentation Slides

Nov. 14, 2022  Public Information Meeting #1 Meeting Presentation Slides

City Process Meetings

Aug. 06, 2024 Common Council File#84340
July 24, 2024 Board of Public Works File #84340
July 22, 2024 Finance Committee File #84340
Awarding Public Works Contract 9502, Warner Park Community Recreation Center Expansion (12th AD) and amending the 2024 Adopted Capital Budgets for Parks Division and Engineering-Facilities Divisions to complete the project.

Apr. 16, 2024 Common Council File #82692
April 03, 2024 Board of Public Works File #82692
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for the Warner Park Community Recreation Center Expansion

Mar. 05, 2024 Common Council File #81984
Feb. 21, 2024 Board of Public Works File #81984
Authorizing the Mayor and City Clerk to amend the contract for Purchase of Services (Architect) with Engberg Anderson, Inc. to provide extra professional architectural and engineering consultant design services and construction administrative services for the expanded design and construction scope at the existing Warner Park Community Recreation Center located at 1625 Northport Drive.

Apr. 26, 2023 Urban Design Commission File #76911

Aug. 02, 2022 Common Council File #72262
July 20, 2021 Board of Public Works File #72262
Authorizing the Mayor and City Clerk to enter into a contract for Purchase of Services (Architect) with Engberg Anderson Architects, Inc. to provide professional architectural and engineering consultant design services and construction administrative services for the existing Warner Park Community Recreation Center building located at 1625 Northport Drive

In the News

Sept. 16, 2024 City of Madison News Update
Warner Park Community Recreation Center Expansion Moves Forward

April 03, 2023 Wisconsin State Journal
Madison moving to expand bustling Warner Park Community Recreation Center

Existing Warner Park Community Recreation Center

WPCRC FRONT ELEVATION
WPCRC_BACK
WPCRC_INTERIOR

Project Updates

December 17, 2024 Update

Watch the construction progress of the Warner Park Community Recreation Center's Expansion available on the live construction site camera.  

October 8, 2024 Update

Quarter 4 Update
Vogel Brothers is preparing to mobilize on site.  In the coming weeks construction fencing will be installed, a construction trailer will be delivered, and some trees in the area of the expansion will be removed. The Center will remain open during the project.  

 

September 16, 2024 Update
July 23, 2024 Update

Bids were opened on 6/27/24.  Five bids were received and all were overbudget.  Resolution file #84340 was introduced to Common Council on 7/16 to amend the project budget and award the low-bid (Vogel Bros. Bldg. Co.).  The resolution was passed by the Finance Committee on 7/22/24 and will be presented to the Board of Public Works on 7/24/24.  Final action by Common Council will be on 8/6/24.

June 25, 2024 Update

Addendum #4 was issued today, June 25th, 2024 and is available with the bid documents on Bid Express.  Bidders are reminded to acknowledge all four addendums with their bid documents.  Bids are due this Thursday, June 27, 2024 at 2:00 p.m.

June 21, 2024 Update

Addendum #3 was issued yesterday afternoon, June 20th, 2024 and is available with the bid documents on Bid Express.  Bidders are reminded to acknowledge all addendums with their bid documents, due next Thursday, June 27, 2024 at 2:00 p.m.

June 14, 2024 Update

Addendum #2 was issued today, June 14th, 2024 and is available with the bid documents on Bid Express.  Bidders are reminded to acknowledge all addendums with their bid documents, due on June 27, 2024 at 2:00 p.m.

May 31, 2024 Update

The Bid Talk Meeting Recording for the Warner Park Community Recreation Center Expansion is now available: 

May 31, 2024 Bid Talk Recording

May 28, 2024 Update

Two important reminders to bidding contractors for this week.

The first of two planned contractor project tours will be held this Wednesday May 29, 2024 2:00 p.m. at the project site, 1625 Northport Drive Madison, WI

Please join us on Friday, May 31, 2024 at 11:00 a.m for a Contractor's Bid Talk which will be held virtually.  Preregistration is required at Bid Talk: Warner Park Community Recreation Center Expansion Registration.  All contractors are invited to attend the virtual meeting which will include a brief presentation of the project and a chance to ask questions.  

 

May 20, 2024 Update

The project status has been updated to BIDDING!  Please see the Project Schedule for links to the bid documents and dates for the virtual contractor Bid Talk, SBE meetings and upcoming contractor pre-bid site tours.

A Flickr album has been created for the Warner Park Community Recreation Center Expansion.  Future photos will be added to share construction progress.

March 29, 2024 Update

This project is on the Board of Public Works agenda on April 03, 2024 and City Council on April 16, 2024.  File #82692 Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for the Warner Park Community Recreation Center Expansion.

February 19, 2024 Update

This project is on the Board of Public Works agenda on Feb. 21, 2024 and City Council on Mar. 05, 2024.  File #81984 Authorizing the Mayor and City Clerk to amend the contract for Purchase of Services (Architect) with Engberg Anderson, Inc. to provide extra professional architectural and engineering consultant design services and construction administrative services for the expanded design and construction scope at the existing Warner Park Community Recreation Center located at 1625 Northport Drive.

November 8, 2023 Update

Due to some setbacks beyond the City’s control, the project has been delayed until January. The project schedule will be affected by this delay.  The project will likely bid summer of 2024.

Was this page helpful to you?